
Continued From Previous Page...
Lindbergh Relocation -North Roads
Client: HDR
Owner: City of St. Louis/ MoDOT
Completion Date: Mar 2002
Const. Value: $10,000,000
As a subconsultant
ABNA is responsible for topographic surveys, drainage, and utility design
for a series of three ancillary road projects associated with the
expansion of St. Louis Lambert Airport. The contract involves the design
of relocated Lindbergh north of the new
Lindbergh Tunnel, relocated Missouri Bottom
Road, and the Temporary North Lindbergh Bypass.
One particular challenge of this project
is that each of the three roads will be let separately for construction
but all three designs must be coordinated as one project. Drainage
elements include culverts, area inlets and drop inlets. Utility design
includes duct banks for electrical and mechanical elements as well as
relocating and designing sanitary and combined sewers to accommodate the
new surface flow. ABNA is also responsible for designing a local road
that will be included in the Lindbergh portion of the job.
Lindbergh/Natural Bridge Interchange
Owner: City of St. Louis/ MoDOT
Completion Date: Oct 2001
Const. Value: $10,000,000
ABNA was a
joint-venture partner on the design of the interchange connecting the new
alignments of Natural Bridge Road and Lindbergh being relocated for the
Lambert Airport Expansion project. For this effort ABNA was responsible
for designing an 1800’ 5-lane section of Natural Bridge, an 800’ retaining
wall along Lindbergh, a 600’ retaining wall along the HI-Connector, and
slope stability walls for the bridge. We also prepared plans for the
lighting and drainage on both Lindbergh and Natural Bridge. There were
three traffic signals that had to be designed for this project to serve
Natural Bridge and the HI collector. ABNA also prepared the traffic
control and construction staging plans.
|
Natural Bridge Road West
Owner: City of St. Louis/ MoDOT
Owner: City of St. Louis/ MoDOT
Completion Date: Sep 2001
Const. Value: $4,000,000
This project involved realigning existing
Natural Bridge Road about half mile
south of the existing alignment. The 1300 feet long new pavement is two
(2) lane – two (2) way roadway. Also involved is pavement design,
drainage design, detention basin, traffic control and traffic signals. The
challenge on this project is to transition this new roadway pavement to
the Lindbergh interchange which has four (4) lanes. This transition had to
be geometrically fitted within a 300 feet length. ABNA Engineering is the
design engineer responsible for the realignment of Natural Bridge West,
all lighting, traffic signals, drainage and traffic control. The roadway
is being relocated 2000 feet South to accommodate the St. Louis Lambert
runway expansion. ABNA is responsible for PS & E.

|