Water - Wastewater    
Home
ABNA Facts
ABNA Services
ABNA in the News
On-Line Brochures
Meet The Staff
ABNA Careers
ABNA FTP Site
ABNA Links
Contact Us
Employee Page
ABNA Chicago
ABNA E. St. Louis

Project Experience

Fee Fee Creek Sanitary Relief

Owner: MSD
Commencement: Jan 2004
Construction Value: $3,200,000

The objective of this project is to provide a design for a sanitary trunk sewer replacement in the Fee Fee Creek watershed.  The new trunk sewer will eliminate surcharging and associated backups and enable the removal of the sanitary sewer overflow (SSO) bypass.  The project reach of trunk sewer is approximately 7,800 feet long and serves commercial and residential properties.  The design considers the staging of the pipe installation to facilitate continued use of the system during the construction phase.  ABNA will also provide the boundary survey and strip map, topographic survey and all easement and working room plats.

North Price to Pernell Sanitary Relief

Owner: MSD
Commencement: Jan 2003
Construction Value: $1,400,000

The objective of this project is to design the replacement for a 1,300 foot reach of sanitary trunk sewer adjacent to River Des Peres.  The design considers the staging of the pipe installation to facilitate continued service to industrial and residential properties facilities during construction.

The depth of pipe installation and associated spaced limitations due to proximity of existing structures and facilities dictates the requirement for tunneling a significant part of the new reach of pipe.  ABNA will also provide the boundary survey and strip map, topographic survey and all easement and working room plats.

Deer Creek Flood Study

Client: U.S. Army Corps of Engineers
Completion Date: Jan 2002

ABNA performed hydraulic analysis on a three (3) mile reach of Deer Creek, using new field information and HEC-1 and HEC-2 computer software.  There were four bridges along this reach that were experiencing flooding and the study was utilized to resize the openings of these bridges along the creek.

Fenton Wastewater Treatment Plant Improvement

Owner: MSD
Commencement: Jan 2004
Construction Value: $3,600,000

ABNA has begun Construction Management work on a $3.6 million project to upgrade a wastewater treatment plant in Fenton, Mo., for Metropolitan St. Louis Sewer District.

The facility will have the capacity to process 6.75 million gallons of sewage per day when complete. The improvement will add two clarifiers, upgrade the aeration system and install piping and instruments to expand the plant's capacity.  It will also add a biofilter to help control odor.

The upgrade will add 10 years to the life of the plant, which eventually will be eliminated when the new Lower Meramec River treatment plant in Oakville is completed.

The project is part of MSD's $647 million capital improvement and replacement program.

Harlem Baden Phase III

Client: MSD
Completion Date: Jan. 2003
Const. Value: $2,200,000

This project involved performing a watershed study of the Harlem Baden area. Questionnaires were delivered to ascertain the level of backup problems in the area. The data collected was then analyzed and imputed into a GIS system. The GIS data base was used to determine the location of the worst backup problems and areas where I/I was evident when there was a major rain event. The watershed area was then broken into 3 sub watersheds and the combined sewer problems were then addressed with relief sewers and addition of new inlets and manhole structures. Some pipe reaches were lined to reduce inflow and Infiltration. A new detention basin was designed to further reduce inflow from surface drainage into the combined sewer system.

 

Webmaster: Daniel R. Taylor
Copyright © 1999 - 2008 ABNA Engineering, Inc. All rights reserved.
Revised: February 08, 2008